To enable works on the roundabout being constructed for the Botley bypass two-way traffic lights will be in operation from Monday 30 March until Friday 24 April on the A3051, from 9.30am until 4pm and until Saturday 25 April on the A334 overnight 8pm to 6am.
The pedestrian and cycle access will remain throughout on signed routes.
These lights should be removed over the Easter Bank holiday weekend and on weekends.
Complete closures of the A3051 are planned to take place from late May to early June (delayed from Easter), aligning with the summer half term school holiday.
For full details see HCC’s website